Cost

After meeting with the Principals for the 1-on-1 meetings, the Master Plan diagrams were revised. Estimated costs were developed, aligning with the Master Plan diagrams.  

All costs shown are in 2020 dollars. For planning purposes, once a project moves forward to Board approval, the District’s facilities department should escalate these costs to the midpoint of project construction.

The following items are excluded from this budget:

  • Utility hook-up fees & City connection fees
  • Off-site work and traffic signals
  • Land acquisition costs
  • Temporary classrooms
  • Hazardous material surveys, abatement and disposal
  • Escalation (costs are in 2020$)

Costs reflected herein include a combination of repair needs and long-term visioning:

  • Repair and replacement costs identified in the Facility Needs Assessments 
  • Campus improvements to align with the district’s vision as developed through extensive stakeholder engagement and the Educational Specifications (long-term visioning)