Program Cost

After meeting with the Principals for the 1-on-1 meetings, the Master Plan diagrams were revised. Estimated costs were applied to the Master Plan diagrams.

All costs shown are in 2018 dollars. For planning purposes, once a project moves forward to Board approval, the District’s Facilities & Maintenance should escalate these costs to the midpoint of project construction.

Due to their unpredictable nature, the following items are excluded from the cost estimate:

  • utility hook-up fees & City connection fees
  • off-site work and traffic signals
  • land acquisition costs
  • temporary classroom costs
  • hazardous material surveys, abatement, and disposal
  • escalation (costs are in 2018 dollars)